Capitol Hill Day School Building Addition

Through the upcoming renovation of the Dent building, the School will realize a long term strategic goal of supporting and strengthening our programs by improving and updating our facility.


The School has established this blog to inform parents, friends, neighbors, and students of the status of the project. Please check the site often or subscribe to the RSS feed for notification of when new items are posted.

Tuesday, January 24, 2012

Level 1 Flooring -- January 24, 2012

The final coat of sub-flooring was poured overnight and the crew is completing a fine polish on the surface. Hard to believe after all the discussion this aspect of the renovation project entailed that the job is near completion. I have learned that the Level 1 floor is now "flat," a distinction from "level."



The surface is scheduled for completion Thursday, January 26th.

No comments: