Capitol Hill Day School Building Addition

Through the upcoming renovation of the Dent building, the School will realize a long term strategic goal of supporting and strengthening our programs by improving and updating our facility.


The School has established this blog to inform parents, friends, neighbors, and students of the status of the project. Please check the site often or subscribe to the RSS feed for notification of when new items are posted.

Friday, July 29, 2011

Dent Renovation Progress July 25 - 29






Monarc Construction estimates that it has completed 77% of the demolition work. Nothing remains of the center core but a small pile of rubble. Excavation work on the footings and the elevator shaft shows progress as well.

Picture Captions:

1. Elevator pit. The elevator pit is at the former entrance to the Kindergarten classroom.

2. Loft "Great Space" Sunlight streaming in on the upper left is from the library entrance. The ladder on the right is where the drama closet used to be.

3. The Science Room minus (or now including) the Head of School's former office.

4. The PE Office.

5. Level One. The small opening on the left is the entrance to the PreK under-the-stairwell storage space. The remaining rubble is where the Receptionists' Office was. The construction debris and dirt unearthed from the footings is carried out bucket by bucket by the demolition crew.