Capitol Hill Day School Building Addition

Through the upcoming renovation of the Dent building, the School will realize a long term strategic goal of supporting and strengthening our programs by improving and updating our facility.


The School has established this blog to inform parents, friends, neighbors, and students of the status of the project. Please check the site often or subscribe to the RSS feed for notification of when new items are posted.

Tuesday, June 7, 2011

Kickoff for Construction -- June 22, 2011

Monarc Construction will report to work at the Dent School on Tuesday, June 22nd to begin our building renovation project.

Schedule:

Week of June 22 - June 24: Salvage Work -- Clean out all of the interior furniture, fixtures, remaining classroom items and detritus from the Dent Building. This is called the "Make Safe" phase.

Week of June 27 - July 1: Interior Demolition will begin. Footings will be dug. Interior structural steel will be delivered.

I will keep the schedule updated as many weeks in advance as is feasible.

No comments: