Capitol Hill Day School Building Addition

Through the upcoming renovation of the Dent building, the School will realize a long term strategic goal of supporting and strengthening our programs by improving and updating our facility.


The School has established this blog to inform parents, friends, neighbors, and students of the status of the project. Please check the site often or subscribe to the RSS feed for notification of when new items are posted.
Showing posts with label Drilling. Show all posts
Showing posts with label Drilling. Show all posts

Friday, August 1, 2008

Progress Report, Well Drilling Friday, August 1st


Northern Virginia Drilling reached bedrock at 290 feet late Thursday evening. There appears to be approximately 55 feet of sand strata. The well should generate adequate water flow for the School's intended purposes. The firm will now pipe the well and perform several pump tests to generate data for the engineers at Bowman Consulting. Based on the test data Bowman will determine the size/capacity/functionality of the pumping equipment for the building addition. Thanks to Jack Miller, John Brown, and Kent Wilkes, our drilling team.

Thursday, July 31, 2008

Progress Report -- Drilling a Well


Jack Miller, President, Northern Virginia Drilling Company, and Winfield Sealander, Chair of the Capitol Hill Day School Board of Trustees' Facilities Committee review the status of our drilling project. Northern Virginia Drilling was on site Wednesday and Thursday, July 30-31 to find an adequate source of water for a geothermal HVAC system in the proposed addition to the building. John Brown, Driller, and Kent Wilkes, Assistant Driller worked with Jack on the project.

More pictures and videos of the drilling can be found at the following website: http://www.flickr.com/photos/chds/collections/72157603777742737/

Tuesday, July 22, 2008

Drilling a Test Water Well

On Wednesday, July 30 and Thursday, July 31 Northern Virginia Drilling, Inc., and Bowman Geothermal LC will drill a water well in the School's parking lot. This is a test to determine if we have adequate subterranean water to install an open loop geothermal heat exchanger in the proposed middle building for the School.

Wednesday, July 16, 2008

Porous Concrete Surface for the Parking Lot

We will drill several test holes in the parking lot in early August to determine if we can specify in the construction documents that the building contractor repave the parking lot with a porous concrete surface.

The District of Columbia's building code requires us to contain water that would otherwise run off a roof or a parking lot into the storm sewers. This goal is also important as we try to meet an environmental standard.

Where will rainwater from the parking lot drain? One idea that our Design Building Team is exploring is a porous concrete surface for the parking lot, but we have to determine if this solution is feasible by testing to see if the soil under the existing parking lot is sufficiently permeable.

Several holes will be drilled in the parking lot at various levels into the subsoil to determine the infiltration rate. If it is not fast enough the District will require the construction of an underground chamber filled with with sand and gravel along with an overflow drain to the storm sewer. We will realize cost savings if surface water will infiltrate the soil.

Steve Goley, P.E., LSA Associates, contributed to this post.