Monarc Construction will report to work at the Dent School on Tuesday, June 22nd to begin our building renovation project.
Schedule:
Week of June 22 - June 24: Salvage Work -- Clean out all of the interior furniture, fixtures, remaining classroom items and detritus from the Dent Building. This is called the "Make Safe" phase.
Week of June 27 - July 1: Interior Demolition will begin. Footings will be dug. Interior structural steel will be delivered.
I will keep the schedule updated as many weeks in advance as is feasible.