Fortunately there is a PEPCO transformer on the site. MC Dean will work with PEPCO to activate the transformer, install a connector box and two panels on the modular units then connect the power from the transformer to the modular units.
At this stage of the planning process we expect each modular unit will have its own 8' copper ground.
This electrical work will be permitted through the DC Department of Consumer and Regulatory Affairs (DCRA).
Inspecting the PEPCO transformer, from left to right, Kelly Young, Operations Manager, Capitol Hill Day School, Michael Keatley, Project Manager, MC Dean, and Christopher Regan, the Day School's Project Manager for the swing space installation.